Renewables, nuclear, and data center projects were identified as risk hotspots in HKA’s CRUX analysis of construction claims and disputes.
The London-headquartered risk and dispute consultancy’s ninth annual CRUX report focused on the risk profiles of sectors bound up with the global energy transition. The rolling research program draws on the HKA’s firsthand investigations of claims and disputes on capital and infrastructure projects globally to identify trends, causes, and impacts on budgets and schedules.
The CRUX research now spans 2,410 projects across 122 countries representing $2.56 trillion of investment. The average CapEx per project is $1.19 billion and cumulative sums in dispute have reached $100 billion.
Overall, projects scheduled to complete from 2020 onward have been less likely to experience disputes – reinforcing the improvement reported last year. Incomplete design and scope change decreased by nearly 10% from earlier levels, while average extension of time (EOT) fell to 48.8% of contract schedules and contested costs fell to 28.4% of budgets.
The CRUX report, however, said the cost of project distress remains structurally high. Cost claims on contracts averaged 33% of budgets and EOTs reached 65.8% of planned schedules, little changed from last year’s rolling averages – which were significantly higher than equivalent outcomes for later projects in the dataset.
Change in scope was the largest cause of conflict over the full CRUX timeframe at 33.4% of projects. Three design-related factors – design error (20.8%), late design information (19.7%), and incomplete design (17.2%) – drove claims and disputes on 40.5% of projects.
“Global construction growth remains strong, and risk management is improving, as our research shows. But claims and disputes still cost the industry heavily in time and money,” said Steve Culp, CEO of HKA. “While technology adoption may be contributing to the progress indicated by CRUX, but we don’t believe the industry has yet been able to absorb the potential benefits from AI and other advances.”
Risk in energy transition
Data centers faced the challenge of incomplete and inaccurate designs, which affected almost a quarter of projects, while overruns more than doubled (112%) planned schedules and costs claimed 20.6% of budgets. On projects completing from 2020 onward, EOTs claimed decreased to 67% but costs increased to 30.2%.
Nuclear project overruns approached 50% of contract schedules, driven by political pressure to break ground before completing planning and design.
Renewable energy faced unforeseen conditions (usually ground or seabed) that disrupted 23.7% of projects, while late or restricted access affected a further 18.7%. The HKA data also found rising interface failures – usually involving contractors inexperience in cable-laying.
The Americas
In the Americas deficient workmanship (20.1%) and unforeseen physical conditions (17.4%) resulted in more claims than other regions. EOTs decreased to 44.2% of later schedules while claimed costs increased to 31.8% of budgets.
“Whether it is offshore wind, nuclear generation, or data centers supporting the digital economy, the pressure to deliver at pace can expose weaknesses in planning, design, and execution,” said Toby Hunt, partner and international client lead, HKA. “Understanding where risks emerge, and how they evolve and can be countered is critical to improving outcomes and avoiding costly claims and disputes.”